Skip to content

Photos

Please mouse over photos to see photo captions and click on photos to see a larger view. Photos credited to Alex Herlant.

Petroleum and Cement Terminal

Wrapping up the first phase of PAMP is a significant milestone. Here’s an overview of what it took to complete the PCT.

Link
Survey crews at work before construction begins.
Survey crews at work before construction begins.
Link
Construction begins with pile installation.
Construction begins with pile installation.
Link
Trucks transfer piles from barge to project location.
Trucks transfer piles from barge to project location.
Link
Piles are installed using cranes.
Piles are installed using cranes.
Link
Aerial view of early construction at low tide.
Aerial view of early construction at low tide.
Link
Rebar is an important element to the PCT deck to ensure its ability to withstand earthquake shaking.
Rebar is an important element to the PCT deck to ensure its ability to withstand earthquake shaking.
Link
Concrete pumping and placement.
Concrete pumping and placement.
Link
A rainbow over the worksite.
A rainbow over the worksite.
Link
Concrete is poured to form the PCT platform decking.
Concrete is poured to form the PCT platform decking.
Link
Workers use rebar to reinforce the concrete decking.
Workers use rebar to reinforce the concrete decking.
Link
Workers pour concrete on the platform decking.
Workers pour concrete on the platform decking.
Link
Constructing the PCT’s pile-supported dock.
Constructing the PCT’s pile-supported dock.
Link
Tarps were used to help the concrete cure in the cold temperatures.
Tarps were used to help the concrete cure in the cold temperatures.
Link
Workers lay the concrete needed for the PCT platform deck.
Workers lay the concrete needed for the PCT platform deck.
Link
Workers level concrete decking.
Workers level concrete decking.
Link
Workers spread concrete under a temporary tent to allow for work to continue during cold temperatures.
Workers spread concrete under a temporary tent to allow for work to continue during cold temperatures.
Link
Crews level concrete.
Crews level concrete.
Link
Workers place concrete to join the piles to the pile cap for one of the Access Trestle caps.
Workers place concrete to join the piles to the pile cap for one of the Access Trestle caps.
Link
The PCT trestle and platform decking supported by precast concrete panels and permanent piles.
The PCT trestle and platform decking supported by precast concrete panels and permanent piles.
Link
Installing 144-inch monopiles to support the PCT dolphins.
Installing 144-inch monopiles to support the PCT dolphins.
Link
Installing permanent piles that support the PCT dolphins.
Installing permanent piles that support the PCT dolphins.
Link
Cranes work to install piles that support the PCT trestle and platform decking.
Cranes work to install piles that support the PCT trestle and platform decking.
Link
Constructing permanent piles that support the PCT trestle and platform decking.
Constructing permanent piles that support the PCT trestle and platform decking.
Link
Bubble curtains are used during pile-driving activities to protect marine mammals, including the endangered beluga whale.
Bubble curtains are used during pile-driving activities to protect marine mammals, including the endangered beluga whale.
Link
Constructing the PCT’s pile-supported dock at low tide.
Constructing the PCT’s pile-supported dock at low tide.
Link
In-progress aerial image of the platform decking being constructed.
In-progress aerial image of the platform decking being constructed.
Link
Constructing the hose tower and product lines.
Constructing the hose tower and product lines.
Link
PCT product line construction.
PCT product line construction.
Link
PCT product line construction on land.
PCT product line construction on land.
Link
PCT product line construction.
PCT product line construction.
Link
Aerial view of the new PCT on a sunny day.
Aerial view of the new PCT on a sunny day.
Link
Aerial view of the new PCT.
Aerial view of the new PCT.
Link
The PCT’s hose tower and crane facilitates the offloading of petroleum products and personnel.
The PCT’s hose tower and crane facilitates the offloading of petroleum products and personnel.
Link
New PCT fenders.
New PCT fenders.
Link
Catwalk leads to breasting and mooring dolphins across icy water.
Catwalk leads to breasting and mooring dolphins across icy water.
Link
Breasting and mooring Dolphins serve as satellite locations away from the primary PCT platform that a ship can tie up to.
Breasting and mooring Dolphins serve as satellite locations away from the primary PCT platform that a ship can tie up to.
Link
New mooring and breasting dolphins.
New mooring and breasting dolphins.

  

North Extension Stabilization Step 1 (NES1)

The North Extension was originally built in 2009 and deemed a failure in 2012 by the Municipality of Anchorage and its advisors. Construction on the new alignment began in summer 2023 and will be completed at the end of 2025. Photos showing progress will be added.

Link
Aerial view of the North Extension.
Aerial view of the North Extension.
Link
Groundbreaking at the NES1 site as a cruise ship comes into the Port.
Groundbreaking at the NES1 site as a cruise ship comes into the Port.
Link
Soil strengthening in progress for NES1.
Soil strengthening in progress for NES1.
Link
North Extension sheet pile failure.
North Extension sheet pile failure.
Link
North Extension sheet pile failure.
North Extension sheet pile failure.
Link
Flag flies from the top of the deep soil mixing equipment at the NES1 construction site.
Flag flies from the top of the deep soil mixing equipment at the NES1 construction site.
Link
A derrick barge is used to remove sheet pile pieces from the water.
A derrick barge is used to remove sheet pile pieces from the water.
Link
Workers assist with deep soil mixing for NES1.
Workers assist with deep soil mixing for NES1.
Link
Construction in progress for NES1.
Construction in progress for NES1.
Link
Operations continue as usual during NES1 construction.
Operations continue as usual during NES1 construction.
Link
Armor stone is stockpiled before placement along the new shoreline.
Armor stone is stockpiled before placement along the new shoreline.
Link
Crews remove sheet piles at the North Extension.
Crews remove sheet piles at the North Extension.
Link
Barges during sunset.
Barges during sunset.
Link
Manson’s derrick barge Valhalla is used for in-water dredging.
Manson’s derrick barge Valhalla is used for in-water dredging.

Administration building

The work at the Administration Building is complete. Here are some photos to show how it was done.

Link
Foundation and fill testing.
Foundation and fill testing.
Link
Excavators break ground on the Administration building.
Excavators break ground on the Administration building.
Link
Groundbreaking activities for the Administration Building.
Groundbreaking activities for the Administration Building.
Link
A pile driver breaks ground for the Administration building.
A pile driver breaks ground for the Administration building.
Link
Workers install piles to form the foundation of the Administration building.
Workers install piles to form the foundation of the Administration building.
Link
Pile cap welding.
Pile cap welding.
Link
Pile cap welding in the snow.
Pile cap welding in the snow.
Link
Several piles are installed to form the foundation of the Administration building.
Several piles are installed to form the foundation of the Administration building.
Link
Concrete work begins.
Concrete work begins.
Link
Progress on the Administration Building.
Progress on the Administration Building.
Link
Crews install insulated metal panels on the Administration Building.
Crews install insulated metal panels on the Administration Building.
Link
Worker cutting framing materials for Administration Building.
Worker cutting framing materials for Administration Building.
Link
A worker installs roofing on the new Administration Building.
A worker installs roofing on the new Administration Building.
Link
Workers begin painting process inside the Administration Building.
Workers begin painting process inside the Administration Building.
Link
Snow falls on the Administration Building in November 2023.
Snow falls on the Administration Building in November 2023.
Link
The completed Administration Building.
The completed Administration Building.

Environmental

We share Cook Inlet with many marine mammals and prioritize their protection. Take a look at the Port’s residents and how we are using mitigation measures to lessen the effects of construction.

Link
The waterway is home to the endangered Cook Inlet beluga whale.
The waterway is home to the endangered Cook Inlet beluga whale.
Link
Belugas in the distance.
Belugas in the distance.
Link
Belugas at the Port.
Belugas at the Port.
Link
Belugas at the Port.
Belugas at the Port.
Link
Belugas spotted by the newly constructed PCT.
Belugas spotted by the newly constructed PCT.
Link
The bubble curtain equipment is moved from pile to pile to help protect sea mammals by reducing underwater pile-driving noise that is released into Knik Arm.
The bubble curtain equipment is moved from pile to pile to help protect sea mammals by reducing underwater pile-driving noise that is released into Knik Arm.
Link
Bubble curtains are generated using large air pumps.
Bubble curtains are generated using large air pumps.
Link
Bubble curtains in action during the PCT construction.
Bubble curtains in action during the PCT construction.
Link
Bubble curtains used during PCT construction.
Bubble curtains used during PCT construction.
Link
Close up look at bubble curtains at work.
Close up look at bubble curtains at work.
Link
Bubble curtain around a monopile.
Bubble curtain around a monopile.
Link
Underwater sound monitoring equipment, known as hydrophones, are used to record sound levels during pile driving.
Underwater sound monitoring equipment, known as hydrophones, are used to record sound levels during pile driving.
Link
Workers set up hydrophones.
Workers set up hydrophones.
Link
Workers use hydrophones and keep a look out for belugas. If a beluga is spotted, pile driving will stop.
Workers use hydrophones and keep a look out for belugas. If a beluga is spotted, pile driving will stop.
Link
Marine mammal observers at work during pile driving. Construction will stop if belugas are spotted.
Marine mammal observers at work during pile driving. Construction will stop if belugas are spotted.
Link
Marine mammal observers.
Marine mammal observers.
Link
Marine mammal observers.
Marine mammal observers.
Link
An eagle enjoys low tide at the Port.
An eagle enjoys low tide at the Port.
Link
Harbor seals frequent the Port.
Harbor seals frequent the Port.

  

Link
Bubble curtains surround piles.
Bubble curtains surround piles.

Operations

Cargo activities operate year-round and will remain operational throughout construction. See the Port in action!

Link
Aerial view of Port of Alaska before PAMP.
Aerial view of Port of Alaska before PAMP.
Link
Fog rolls in across the Port.
Fog rolls in across the Port.
Link
The Port supports both cargo and commercial activities.
The Port supports both cargo and commercial activities.
Link
Cruise buses bring passengers to board the ship.
Cruise buses bring passengers to board the ship.
Link
Passengers exit the cruise ship, supporting Alaska’s important tourism economy.
Passengers exit the cruise ship, supporting Alaska’s important tourism economy.
Link
Aerial photo of the cargo terminal.
Aerial photo of the cargo terminal.
Link
Matson is one of two cargo tenants at the Port.
Matson is one of two cargo tenants at the Port.
Link
Matson loading operations.
Matson loading operations.
Link
Tote is one of two cargo tenants at the Port.
Tote is one of two cargo tenants at the Port.
Link
Tote loading operations.
Tote loading operations.
Link
Onboard the Tote vessel.
Onboard the Tote vessel.
Link
The sun sets over the Port.
The sun sets over the Port.
Link
The PCT trestle and product lines leading to the Cement dome in the snow.
The PCT trestle and product lines leading to the Cement dome in the snow.
Link
The Port supports important military activities as this Chinook Helicopter is offloaded.
The Port supports important military activities as this Chinook Helicopter is offloaded.
Link
The military uses the Port to transport tanks.
The military uses the Port to transport tanks.
Link
Ice floes at the cargo docks.
Ice floes at the cargo docks.

  

Link
Tanker docks in ice.
Tanker docks in ice.
Link
Tote Midnight Sun docks behind Matson Kodiak.
Tote Midnight Sun docks behind Matson Kodiak.

Media gallery

For media inquiries, contact Jim Jager, Director of Business Continuity and External Affairs, and Facility Security Officer: Jim.Jager@anchorageak.gov.

Link
Aerial view of the new PCT on a sunny day.
Aerial view of the new PCT on a sunny day.
Link
PCT construction.
PCT construction.
Link
Maintaining operations during construction.
Maintaining operations during construction.
Link
Ice floes limit the in-water construction season to just 6 months per year.
Ice floes limit the in-water construction season to just 6 months per year.
Link
Ice floes at the Port.
Ice floes at the Port.
Link
PCT trestle, crane and catwalk.
PCT trestle, crane and catwalk.
Link
Tugboats bring carto ships to the Port.
Tugboats bring carto ships to the Port.
Link
New PCT product lines.
New PCT product lines.
Link
The new PCT crane operates in cold conditions.
The new PCT crane operates in cold conditions.
Link
Cargo docks on a misty cold morning.
Cargo docks on a misty cold morning.
Link
Port operations.
Port operations.
Link
Cranes are a common sight as construction continues at the Port.
Cranes are a common sight as construction continues at the Port.
Link
Operations continue at the Port during construction.
Operations continue at the Port during construction.
Link
Former Anchorage Mayor, Dave Bronson, visits the completed PCT in October 2022.
Former Anchorage Mayor, Dave Bronson, visits the completed PCT in October 2022.
Link
Former Secretary of Transportation, Pete Buttigieg, tours the Port of Alaska in August 2023.
Former Secretary of Transportation, Pete Buttigieg, tours the Port of Alaska in August 2023.

Don Young Port of Alaska

Address:
2000 Anchorage Port Road
Anchorage, Alaska 99501

For more information or questions about PAMP, please email
portofalaska@anchorageak.gov

Copyright © 2024 Port of Alaska Modernization Program. All Rights Reserved.